7 min read
Glumac, partnering with Turner Construction, signed on to provide engineering services on the fast-track, net-zero P Street design-build project in Sacramento, CA. Tapped to also bring its sustainability-focused knowhow to the team, Glumac compressed the time-intensive workflows that are typically required to support projects with such audacious energy use goals. They did this by formulating a workflow that was equal to the ambition of the project, working with the project team from a shared Revit model using Autodesk BIM 360 Design software for design collaboration. This new level of teamwork helped boost productivity and condensed what are normally months-long project phases into mere days.
The use of software to streamline coordination and reduce rework inadvertently helped reduce the carbon footprint of P Street’s project delivery.
Designing green buildings that work
Glumac, which was recently acquired by Tetra Tech, has always had a commitment to designing building systems that efficiently support comfortable spaces. The firm has wholeheartedly embraced sustainable design, having designed more than 250 LEED-certified projects. Their eagerness to embrace innovation led Glumac to adopt BIM (Building Information Modeling) with Revit building design software before many other MEP firms did, and the firm continues to forge ahead with its use of cloud-based design.
Get the full story in this 2 min, 51 sec video:
Ambitious sustainability goals come with an aggressive schedule
The Sacramento building will be the new home of the California Natural Resources Agency. Undertaken by California’s Department of General Services (DGS), to provide office space for more than 3,400 state employees, the P Street project is targeting a LEED Platinum certification and net-zero carbon use. The 22-story building will include 838,000 square feet of space. DGS decided to undertake the P Street building as a design-build project with an aggressive schedule for both design and construction.
The accelerated project schedule left little time between creating the high-level design concepts and developing the shop drawings the subcontractors would use for fabrication and installation of the building systems. That meant Glumac would have to juggle coordination with the architect and other engineers simultaneously as its team assisted the subcontractors—including Southland Industries, Redwood Electric, and Intech Mechanical—to develop shop drawings.
“We turned to BIM 360 Design to accelerate the design and coordination process and help the whole team work more closely,” says Jennifer Berg, an electrical engineer and project manager with Glumac. “Being able to share models within and across offices helped our team work more efficiently on projects in the past, but this was our first BIM 360 Design project where we shared our Revit models with other parties. It required a lot of trust, but it looked like our best option for delivering the project efficiently.”

Jennifer Berg (right) and Tim Totin (left) worked on the same design models in Glumac’s Irvine office with collaborators from four west coast offices in the United States.
Better, greener designs thanks to close collaboration
Meeting sustainability goals required both smart design choices—like fins to shade windows—and advanced MEP technology, including radiant floors, chilled beams to replace traditional HVAC vents, solar panels, and more. The building will even use graywater and rainwater for flushing toilets.
As the Glumac team developed the building systems, its team used BIM 360 Design to co-author the structural and architectural models in Revit. Basically, the teams coordinated together in the BIM 360 platform, concurrently iterating on the models to accelerate the design process while also bringing the contractor into their process. This approach helped everyone take constructability into account as the sustainable design collaboration progressed.
Berg explains the advantages of shared models: “Often, our engineering designs get modified on the fly during construction for space or other considerations. Clearances and other aspects can stray from what we intended. That leads to expensive rework in the field, which has a monetary, time, and environmental cost.”
“But when we’re all working together in BIM 360 Design, we can explore issues in the model in real time. You avoid problems and go into construction with a better design.”
A more sustainable design process
When the concepts were finished, Glumac and the subcontractor jumped right into the shop drawings—bypassing the detailed design phase. BIM 360 Design made that possible because both teams could see and work from each other’s models, making corrections and exploring issues collaboratively as needed. Cloud collaboration helped the team cut back on travel and all the carbon emissions associated with travel. Plus, they used essentially no paper on the project.
“We went straight from the concept to helping create the detailed shop drawings,” says Nick Gallucci, managing director at Glumac.
“That was possible because we were connected to the whole team, especially the MEP subcontractors. We saved time, traveled less, and virtually eliminated the use of paper with help from BIM 360 Design. If you think about it, we reduced the carbon footprint of the project itself.”
Extending the team across borders
The Glumac team traveled less than expected on the project, but it was able to assemble the most qualified team to deliver the net-zero design. How? BIM 360 Design let Glumac include team members from multiple office locations. “People from our Los Angeles, Irvine, and San Francisco offices worked together seamlessly with staff from the multiple project member firms, all in real time,” says Berg.
“BIM 360 Design offers an efficient way to staff projects based on who is available rather than on location. It’s much more sustainable than moving people around for days or weeks at a time.”

Nick Gallucci (left) visits Glumac’s Sacramento office with Tim Totin (right) where the P Street project is currently undergoing construction.
Close sustainable design collaboration saves coordination hours
As new project delivery methods connect teams in ways traditional methods can’t match, general contractor Turner Construction anticipates that the collaborative approach used on the P Street project will become more common. For instance, beyond using BIM 360 Design to coordinate with architects and engineers, Turner also uses BIM 360 Build to collaborate on QC inspections, checklists, and issues, significantly minimizing the amount of paper used and time required for these processes on the jobsite.
Adam Della Monica, project engineer at Turner Construction, explains: “Turner uses Revit models for preconstruction, quantity estimation, and model coordination. With BIM 360 Design, we can work directly with design model instead of waiting for prints or updates.”
“Close collaboration creates value. It helped make P Street’s sustainability goals a reality. Sharing real-time design information is critical to design-build projects,” says Adam Della Monica.
Gallucci points to trust and BIM 360 Design software as key contributors to the time savings. He says: “Too often, engineers think contractors will cut corners, and contractors think engineers will add fluff to models. Sharing brought a heightened level of trust that helped us to collaborate to develop a more sustainable design—and use a more sustainable design collaboration process.”
Glumac estimates that between its team and the subcontractor’s team they saved more than 400 work hours on the project. Gallucci ends on this note: “BIM 360 Design united our teams around common models, and we saw each other’s perspective like never before.”